Two children, a dog and eight weeks in temporary accommodation. A Sunshine Coast family had to put their belongings into storage while waiting to move into a new home that was nearing completion.
The homeowner sought about $13,427 from the builder. More than three years after the claim was lodged, the Queensland Civil and Administrative Tribunal (QCAT) awarded $1,815 and dismissed the remaining claims.
A small figure in the building contract made a big difference: $15 per day.
The Courier Mail reported the dispute on 26 November. The Queensland Judgments index records the decision of 2 November. Here is how the award was calculated, according to the report.
A July move-in that became a December move-in
According to court documents cited by the newspaper, the original contract price was about $245,000. Upgrades brought it to about $280,000, and the owner later signed a further $27,500 price adjustment.
The home was under construction in 2022, with completion originally expected around mid-year. Building material prices, labour shortages and construction delays were familiar problems in the Australian building industry at the time.
Extensions pushed the completion date back.
The family was renting a home for $640 a week and repeatedly asked when their new house would be ready. Their lease was extended, but by October the rental had been let to the next tenant and the family had to leave.
They spent the following weeks arranging temporary accommodation and storing their belongings. They finally moved into their new home in mid-December.
Why did a claim exceeding $13,000 result in an award of $1,815?
The owner sought about $13,427 from QCAT for additional rent, temporary accommodation, storage and contractual delay damages. The reported line items do not reconcile with the stated total, so we have not reproduced the breakdown.
The tribunal handed down its decision on 2 November 2026. The reported award and daily rate imply compensation for 121 days.
The contract specified delay damages of $15 per day.
121 days × $15 = $1,815.
A contractual daily rate can be very different from the costs an owner actually incurs.
The newspaper reported that the tribunal acknowledged the family’s hardship but considered itself unable to rewrite the agreed contractual rate.
Check this line in your building contract
Liquidated damages are an amount agreed in advance to compensate for a specified breach. Some building contracts refer to late completion damages.
When planning a new home, it is easy to spend weeks deciding on the floor plan, kitchen benchtops, flooring and bathroom fittings. Even a relatively small upgrade can receive considerable attention.
But how much thought goes into the daily amount payable if the house is late?
Suppose a household faces weekly rent of $650 and storage costs of $70. That is more than $100 a day in additional expenses.
Over a hypothetical 90-day delay, the difference between contractual damages of $15 and $100 per day is $7,650. This is an illustration, not a standard entitlement or a guarantee of recovery.
The Queensland Building and Construction Commission (QBCC) provides guidance on contract issues, including compensation for late completion. Not every contract contains such a clause.
Before signing, consider the contractual completion date, the conditions under which the builder may obtain extensions, and whether the agreed daily amount reasonably reflects likely losses. Seek independent professional advice where necessary.
Each contract and dispute is different. This decision does not establish that all Australian homeowners can recover only the amount specified in a delay damages clause.
What if the builder goes bust or asks for more money halfway through?
These are often even bigger concerns than a late handover. Does building warranty insurance cover delays? Who arranges the insurance? Can a builder increase the price under a fixed-price contract?
In Queensland, eligible residential building work may have home warranty protection for non-completion and defects, but an ordinary delay alone is generally not covered. Building insurance schemes differ between states and territories.
APOA community members recently discussed another question: if a builder’s base quote is $600,000, will an additional $200,000 really cover the rest?
Read our earlier article: A $600,000 base building quote: will $800,000 really be enough?. That guide discusses Victorian arrangements, which should not be assumed to apply in Queensland.
We will explore builder insolvency, warranty insurance and price increases separately as further real cases arise.
News sources and references
Courier Mail — original report, 26 November 2026
QBCC — building contract issues
QBCC — home warranty non-completion claims
Other property news today
01 | Eight homes demolished after years of building defects
The Northern Territory Government acquired and demolished eight homes with serious building defects in Bellamack after more than a decade of disputes. The land is due to return to auction on 8 December.
Should buyers commission independent inspections on newly built homes? Where can owners turn if serious defects emerge?
ABC News — original report, 25 November 2026
02 | The least affordable rental region is outside a capital city
The 2026 Rental Affordability Index identifies regional Queensland as the least affordable region covered by the index for a fourth consecutive year. Its median rent represents about 33% of average rental-household income.
For owners seeking high rental yields in regional towns, local incomes and rental affordability deserve attention too.
ABC News — report, 24 November 2026; SGS — 2026 Rental Affordability Index, 23 November
03 | Victorian property managers’ registration can now be checked
Since 25 November, Victorian agent’s representatives have been required to register. Owners can check the public register for relevant registration details.
A matching name in the register does not establish that an email requesting a change to bank details is genuine. Verify such instructions independently.
Consumer Affairs Victoria — announcement, 25 November 2026; public register
What should we cover next?
Which of today’s topics would you like APOA to explore in more detail?
1. Builder insolvency: how much can home warranty insurance cover?
2. Can a builder increase the price under a fixed-price contract?
3. Independent inspections and building defect disputes.
4. Regional investment properties: are high rental yields enough?
5. Checking agent credentials and changing property managers.
Contact APOA’s community editor Xiao Wang in our WeChat groups, or email admin@apoa.org.au.
If you have built a home, what daily delay damages rate did your contract specify? We welcome your experiences.
Compiled by the Australian Property Owners Alliance (APOA) from English-language media, tribunal decisions and public official sources. General information only; not individual legal or investment advice. The feature story relies on the reported extracts from the decision and the public case index. The full decision could not be retrieved again for this publication check, and any subsequent appeal has not been verified. The cover is an AI-generated editorial illustration, not a photograph of the property involved.